Case study · Hotel · Cooling tower programme
Cooling tower programme and bleed-off automation at a hotel.
Manual blowdown was replaced with conductivity-controlled bleed-off and a revised inhibitor programme.

- Cycles of concentration
- 3.2 → 8
- Reduction in make-up water
- 28%
What we found.
The hotel's cooling tower was bled off by hand. Manual blowdown cannot follow the load, so towers are usually bled conservatively, running at low cycles of concentration and sending treated water to drain that could have been reused. The tower ran at 3.2 cycles.
What we did.
- Manual blowdown replaced with a conductivity controller and automatic bleed valve
- Setpoint based on the site's water analysis
- Inhibitor programme revised to run safely at higher cycles
- Monthly testing and written reports to confirm control
Measured before and after.
Cycles of concentration rose from 3.2 to 8 and make-up water fell by 28%. Less make-up also means less treated water and chemical sent to drain.
Client name withheld. Figures measured on site and reported to the client.
The services behind this result.
Cooling tower chemical treatment
Scale and corrosion inhibitors, oxidising and non-oxidising biocides and Legionella control.
Learn more →02Cooling tower maintenance
Monthly servicing, physical cleaning and Legionella control for cooling towers across Malaysia.
Learn more →03All six services
Chemical dosing, dosing systems, bleed-off control, filtration, loop flushing and tower cleaning.
Learn more →04Conductivity controller & auto bleed-off
The service used on this job, on our services page.
See the service →